7000+ Electrical Power Sources MCQ Questions & Answers - 3
Question: 11
Which one of the following is neglected while analysing a short transmission line?
(A) Series impedance
(B) Power losses
(C) Shunt admittances
(D) None of the above
Ans: C
Shunt admittances
Question: 12
Gas turbines is widely used in
(A) Aircrafts
(B) Automobiles
(C) Locomotives
(D) Pumping stations
Ans: A
Aircrafts
Question: 13
Equipment used for pulverizing the coal is the
(A) Burner
(B) Ball mill
(C) Hopper
(D) Stoker
Ans: B
Ball mill
Question: 14
In hydroelectric power plants
(A) Operating cost is low and initial cost is high
(B) Operating cost is high and initial cost is low
(C) Both operating cost as well initial cost are high
(D) Both operating cost as well as initial cost are low
Ans: A
Operating cost is low and initial cost is high
Question: 15
In a steam power plant water is used for cooling purposes in
(A) Superheater
(B) Boiler
(C) Condenser
(D) Economiser
Ans: C
Condenser
Post Harvest Engineering of Horticultural Crops, Cereals, Pulses, Oilseeds More
Dairy and Food Engineering MCQ Questions Pdf More
Nuclear Physics Questions for Class 10 with Answers Pdf More
Samacheer Kalvi Class 10 Science Nuclear Physics Questions More
Class 10 Science Acoustics Exam Questions & Answers Pdf More
Problems on Time and Distance TNPSC Questions More
100+ Speed, Time and Distance Questions and Answers Pdf More
7000+ GATE Mechanical Question Paper with Solutions Pdf More
Top 100+ Verbal Reasoning Analogy Questions and Answers More
Puzzles Tips and Tricks for Bank PO, SO, Clerk Exams More